When Taos Municipal School District requested that Phase I of the Taos High School Athletic Fields be complete in under three months, Living Designs Group delivered the design, construction documents and the contract for on-time construction. LDG went beyond the architect’s call to provide not only the scope, but to schedule, communicate, and execute the project.

By designing a unique, multi-permit, phased schedule for the THS athletic fields, LDG delivered a fast-tracked Phase I design allowing for completion of the football field with running track and grandstands by the August 2009 Homecoming game. This strict schedule conformance was achieved through our team’s diligence effort to keep the design process on task. The LDG Team provided rapid design iterations and pursued constant feedback from the team, coaches, administrators, and project planning staff to hone the design and incorporate client input in the process.

Phase II of the project includes the Baseball Field and Park, dedicated early in the 2010 Spring season. Phase III, which will complete the athletic complex, includes expansion of the football field grandstands, finished landscaping and a 10,800gsf Field House hosting concessions, public restrooms, press boxes, locker rooms, field storage, and flexible training facilities.

THS Athletic Fields

Taos, New Mexico

Multi-phase High School Sports Complex